If you’re a Queensland tradie or subcontractor owed money, you don’t have to wait months for court or beg your head contractor to pay. The Building Industry Fairness Act 2017 (BIF Act) gives you a statutory right to lodge a payment claim and trigger a legal process designed to move fast. It’s not flashy, but it works—and thousands of small construction businesses rely on it every year.
This post breaks down how the BIF Act works in practice, what you need to do, and where to start.
What Is the Queensland BIF Act?
The Building Industry Fairness Act 2017 is Queensland’s version of Australia’s Security of Payment legislation. Every state and territory has its own version—NSW has the Security of Payments Act 1999, Victoria has the Building and Construction Industry Security of Payment Act 2002, and so on—but they all follow the same basic principle: construction workers shouldn’t have to wait forever to get paid.
Under the BIF Act, if you’ve done work or supplied materials on a Queensland building or construction project, you have the right to serve a payment claim on the person who owes you money (usually your head contractor or direct client). They then have a set time to respond, and if they don’t pay or dispute the claim properly, you can apply for fast-track adjudication to force a decision.
The key word here is fast. Unlike a court case, adjudication is meant to happen in weeks, not years.
Who Can Use the BIF Act?
The BIF Act covers most of the construction supply chain:
- Subcontractors (plumbers, electricians, concreters, carpenters, etc.)
- Suppliers of materials or plant
- Labour-hire providers
- Professional services (engineers, architects, surveyors on construction projects)
- Head contractors claiming against principals
You’re eligible if your work or goods were supplied under a construction contract (or related to one) in Queensland. The project itself doesn’t have to be in Queensland—what matters is that the contract is governed by Queensland law.
One important note: if you’re an employee paid wages, you’re not covered. The BIF Act is for contractors and suppliers operating as separate legal entities.
The Key Steps Under the BIF Act
Here’s how the process actually works, step by step:
- Serve a payment claim. You create a written claim stating how much you’re owed, for what work or goods, and the due date. It has to be detailed enough for the other party to understand what they’re being asked to pay for. This isn’t a casual email—it’s a formal notice under the Act.
- Wait for a payment schedule. The respondent (the person who owes you) has 10 business days to either pay you, or send back a payment schedule explaining what they’ll pay and when.
- If they don’t respond properly, move to adjudication. If they ignore your claim, pay part of it, or send a dodgy payment schedule, you can apply for fast-track adjudication. An adjudicator (an independent third party) reviews the claim and makes a binding decision within a tight timeframe.
- Enforce the adjudicator’s decision. If the adjudicator rules in your favour and the respondent still won’t pay, you can take the decision to court and enforce it—similar to enforcing a court judgment.
The beauty of this system is that the respondent has to take you seriously from day one. If they ignore your claim or give a wobbly response, they’re the ones who end up in front of an adjudicator under time pressure, not you.
Common Mistakes to Avoid
Most Queensland tradies who struggle with the BIF Act make one of these errors:
- Serving the claim carelessly. The claim has to be served on the right person, in the right way, and within the right timeframe. Getting this wrong can derail your whole case.
- Not including enough detail. If your claim is vague (“labour and materials—$5,000”), it’s easier for the respondent to dispute or ignore. Be specific: dates, scope of work, amount per item if possible.
- Missing the deadline for adjudication. You can’t just lodge a payment claim and sit on it. If the respondent doesn’t pay or respond properly, you need to act within the statutory window or you lose your right to adjudicate.
- Serving the claim to the wrong entity. If you worked for Acme Constructions Pty Ltd, you need to serve the claim on that company—not the site manager, not the parent company, not a guess.
These aren’t technical gotchas that only lawyers know about. They’re the basic rules of the game. Get them right, and you’ve got a real shot at a quick resolution.
Getting Started: Your Practical Next Steps
If you’re owed money and you’ve done work in Queensland, here’s what to do:
- Gather all documentation: invoices, contracts, proof of work (photos, delivery dockets, timesheets), emails about the work and payment terms.
- Work out exactly how much you’re owed and for what. Write it down clearly.
- Identify who the right party to claim against is—this is usually your direct client or head contractor.
- Prepare your payment claim (or use a service like file a payment claim to draft it for you).
- Serve it properly—hand-delivered, by post, or by email if the recipient agrees. Keep proof of service.
- Record the 10 business day deadline for their response.
- If they don’t pay or give a proper payment schedule by that deadline, prepare for adjudication.
The BIF Act is there for you. It’s not perfect, but it’s a genuine alternative to waiting six months for a court hearing or writing off the debt altogether.
The Bottom Line
Queensland’s Building Industry Fairness Act isn’t a magic wand, but it’s a tool that works. It gives you a legal pathway to chase money owed under construction contracts, and it forces the other party to take your claim seriously on a tight timeline. If you’re owed money on a Queensland project, understand the BIF Act, follow the steps, and don’t let bad debtors drag you around. Most head contractors and clients know the rules—make sure you do too.
Ready to prepare your own payment claim?
PayClaim helps Australian tradies and subcontractors prepare a Security of Payment Act payment claim online. Flat $79. No subscription. No big debt-collector commission. PayClaim is not a law firm and does not guarantee any outcome.
Owed money? You can start your Letter of Demand here — see the whole letter free, then a flat $69 to issue it. PayClaim is not a law firm; payment outcomes are not guaranteed.
Information on this page is general only and does not take account of your individual circumstances. PayClaim prepares and serves payment claim documents based on the information you provide. PayClaim is not a law firm and does not provide legal advice, adjudication representation, debt collection or court enforcement. Payment outcomes are not guaranteed.