“How long will this take?” is one of the first questions subcontractors ask when considering a Security of Payment claim. The answer depends on which state you’re in and how the head contractor responds — but the Security of Payment process is specifically designed to be fast. Here’s a realistic timeline for what to expect.
The Short Answer
From serving a payment claim to receiving a determination: typically 3–6 weeks. If the head contractor pays after receiving the payment claim (without needing adjudication), often faster — sometimes within 15 business days.
The Timeline, Step by Step
Day 1: Payment Claim Served
Your payment claim is served on the head contractor. This starts the clock. The claim can be served any time on or after the reference date in your contract.
Days 2–10 (or 2–15 in QLD): Payment Schedule Deadline
The head contractor has a set number of business days to respond with a payment schedule:
- NSW, VIC, SA, TAS, ACT: 10 business days
- QLD: 15 business days
- WA: 14 calendar days
- NT: 14 calendar days
Three things can happen at this stage:
- They pay the full amount — done, no adjudication needed
- They issue a payment schedule accepting part of the claim — you may receive partial payment and proceed to adjudication for the balance
- They issue a payment schedule disputing the full amount — you proceed to adjudication
- They do nothing — the full amount is owed and you can apply for adjudication or court enforcement
Days 10–20: Adjudication Application Lodged
If the claim is disputed, you have a short window to lodge an adjudication application:
- NSW, VIC, SA, TAS, ACT: 10 business days from receiving the payment schedule
- QLD: 30 business days from payment schedule (or due date)
- WA, NT: 28 days from the payment response (or when it was due)
Days 20–35: Adjudication Decision
After the adjudicator accepts the application, they have a set time to make a determination:
- Most states: 10 business days (can be extended by agreement)
- WA: 14 days
Days 35–40: Payment (or Enforcement)
If the adjudicator determines in your favour, the head contractor typically has a short period to pay. If they don’t, you can register the determination as a court judgment and pursue enforcement.
What Speeds Up or Slows Down a Claim?
Factors that speed things up:
- Clear, well-documented claim with strong evidence
- Head contractor who responds quickly (even if disputing)
- Adjudicator who acts promptly within their timeframe
Factors that slow things down:
- Complex disputes requiring extensive documentary evidence
- Extended adjudication timeframes (agreed between parties)
- Enforcement required after a non-paying head contractor
PayClaim’s Typical Outcome Timeline
Most PayClaim clients receive payment — or a favourable adjudication determination — within 10–20 business days of starting their claim. Many head contractors pay promptly upon receiving a formal payment claim, before adjudication is even necessary. Start your free claim today and find out how quickly we can get you paid.
Information on this page is general only and does not take account of your individual circumstances. PayClaim prepares and serves payment claim documents based on the information you provide. PayClaim is not a law firm and does not provide legal advice, adjudication representation, debt collection or court enforcement. Payment outcomes are not guaranteed.